01/03/2016, Synergy Power contined to be selected as a provider and installer for the stand-by generator system for the Clinker Viglacera factory project (2nd phase) by Clinker Viglacer Co., Jsc, according to selected bidder result announcement No.59/TB-CT
Project information:
Package: Generator
Project: Expanded investment project (2nd phase), the capacity of 2 million m2/ year, increase the capacity to 4 million m2/ year, Clinker Viglacera factory.
Address: Kim Son commune, Dong Trieu district, Quang Ninh province
Content:
Supply and install 01 generator and auxiliary system including reserved oil tank and ACB cabinet
Form of contract: lump-sum contract
Execution time: 50 days from the date of the contract taking effect